MRS (Multi Resource Scheduling) -
Configuration Guide
|
|
Written by MRS Expert
|
|
Tuesday, 17 March 2009 16:43 |
|
The time allocation types defined in the previous step must be assigned to resource types. Then only they can be used in Planning board.
Activities to be performed are: - Choose a resource type
- Navigate to 'Assign Time allocation types' by double clikcing
- Enter the time allocation types manually or seelct then from F4 list
- Save your work
Note: The resource types 00(Human Resource), 01(Tool Resource) and 99(Team Resource) are delivered by SAP and must not be changed.
Define Time Allocation Type for Tools You also have to specify a time allocation type with which the availabilities of the tool are to be created in MRS Basis. This time allocation type is required when the tool is used for the first time. Example: AVAIL. This time allocation type must have availability type '1-Available' and exception indicator set to space
|
|